Roster · 8 min read · 2026-11-26
Construction crew timesheet (tareo) in Excel: columns, filling, limits
Construction crew timesheet (tareo) in Excel: the columns, filling it by cost item, why it isn't the attendance record, and when Excel falls short.
A construction crew timesheet in Excel (what Peruvian sites call «tareo») is the sheet where the foreman records, every day, how many hours each worker put in and against which cost item of the budget. It carries the project details, one row per worker with ID number, trade category, cost item, regular and overtime hours, and the signatures of whoever filled it in and whoever reviewed it. It's used to pay daily wages and to control labor cost. It is not the attendance record.
This guide is for the site administrator, the payroll clerk and the foreman. It covers the columns the sheet needs, how to fill it so it serves cost control and not just payroll, what separates it from the attendance record Peruvian law requires, and the point where Excel stops being enough.
Timesheet and attendance record are not the same thing
This is the mix-up that costs the most in a labor inspection. DS 004-2006-TR requires every private-sector employer in Peru to keep a permanent attendance record in which each worker records their working time «personally». Since 2008 that duty explicitly covers staff that contractors and subcontractors assign to the site. At a minimum the record holds the employer's name and tax ID (RUC), the worker's name and ID number, the date, hour and minute of clock-in and clock-out, and any time the worker stays beyond the working day. It can be physical or digital, with safeguards against tampering, and it must be kept for five years.
The timesheet is filled in by the foreman, not the worker, so it can't do that job. And Peru's labor inspection regulation (DS 019-2006-TR, item 25.19) classifies as a very serious infraction not having the attendance record, or preventing or replacing the worker in recording their own working time.
In practice the site keeps both: attendance, which the worker clocks, and the timesheet, which splits those hours across cost items. What has to happen every day is that they match.
The columns a construction timesheet needs
The header, once per sheet:
- Project and work front. Project name, front or sector, and the client if the company runs several projects at once.
- Employer and tax ID. If subcontractors work the same front, one sheet per company. Mixing them is the first reconciliation error.
- Date or week covered, and the shift if the site runs two.
- Foreman who fills it in and who reviews it (field engineer or resident engineer).
The body, one row per worker:
- No., full name, ID number. The ID is the key for matching against attendance and payroll. Without it, matching happens by name, and names get spelled differently every week.
- Category: skilled worker, semi-skilled or laborer («operario, oficial, peón»), or whatever the contract defines.
- Crew. Concrete, formwork, rebar, earthworks.
- Cost item. The code from the budget or cost-control system, not free text. "Slab pour" and "3rd-floor slab" are the same item written twice.
- Regular hours and overtime hours, in separate columns.
- Notes. Absence, medical leave, permission, transfer to another front.
At the bottom: total workers, total regular and overtime man-hours, and man-hours per cost item. That last total is what the technical office compares against progress.
How to fill it so it serves cost control
- 1. Fill it at the work front, the same day. A timesheet assembled from memory on Friday allocates hours by habit, not by what actually happened.
- 2. One worker can have two cost items. If a carpenter spent three hours on formwork and five on a pour, that's two rows or two cost-item columns. Loading everything onto the main item is what later makes productivity "improve" on one item and collapse on another.
- 3. Timesheet hours can't exceed attendance hours. If attendance says the worker left at 17:10 and the timesheet books overtime until 19:00, one of them is wrong. DS 004-2006-TR also presumes that time a worker spends on site before clock-in or after clock-out is overtime, unless there's objective proof otherwise. Attendance wins.
- 4. The field engineer checks it against the daily report. Cost-item man-hours against the day's measured quantities. If the rebar crew logged 80 man-hours and the daily report shows no rebar progress, the question gets asked that same day.
- 5. The administrator closes the week. Consolidates the daily sheets, reconciles against attendance and passes it to payroll. That consolidation is where Excel starts to hurt.
Where Excel breaks
For a site with 80 workers and one front, a good spreadsheet is enough. What breaks it isn't the number of rows but what has to be cross-checked:
- One sheet per foreman, per front, per day. With 15 foremen that's 90 files a week, which someone copies into a master file by hand on Monday.
- Cost items get written differently. Without a closed list, the master file holds four versions of the same item and man-hours per item can't be added up.
- The timesheet doesn't match attendance and nobody sees it in time. The gap shows up when the worker disputes their pay, not when it could have been fixed.
- Subcontractors send their own format, each with its own columns. Reconciling the hours they'll invoice against the hours you saw on site becomes another spreadsheet.
- Cost arrives late. If man-hours per cost item are known two weeks later, the item that went over budget has already gone over.
Among the mining and construction contractors we work with, the point where Excel stops being reliable for decisions sits between 3,500 and 4,500 colaboradores per project. But the symptoms above show up much earlier, from the second work front.
Running the timesheet outside Excel
The format doesn't change. The columns are the same. What changes is where it's filled in and what happens next:
- The foreman fills it in on a phone, at the front, picking the cost item from the budget list instead of typing it.
- The timesheet is matched automatically against attendance for the same worker and day. Whatever doesn't match is flagged before the close.
- Man-hours per cost item are visible the next day, next to progress, not at month-end.
- Subcontractors fill in the same system, with their people kept separate, so their valuation comes from the same hours seen on site.
At Logiflex, Timesheet & Attendance is one of our accelerators: deployed 12 times, in production in four to six weeks, adjusted to each project's cost items and formats. A product version is on the way, Logiflex Roster, which joins the digital timesheet with shifts, canteen, lodging and transport. For shift progress and equipment hours there's the Daily Report app, still on a waitlist.
A real case: CUMBRA at Quellaveco
At Quellaveco, Anglo American's copper project in Moquegua, CUMBRA ran several work fronts under EPC pass-through with 7,000 colaboradores. People tracking, valorización, food service and warehouse ran on distributed Excel sheets that couldn't keep pace with the project, with daily roster reconciliation across subcontractors. With Logiflex's accelerators, 42,943 man-hours were digitized, more than 1,400 colaboradores were tracked day by day, and the valorización cycle dropped to under 24 hours.
Frequently asked questions
What is a construction timesheet (tareo)?
It's the daily record of how many hours each worker put in and against which cost item. The foreman fills it in and the field or resident engineer reviews it. It's used to calculate daily wages and to see how many man-hours each budget item consumes.
Does the timesheet replace the attendance record?
No. DS 004-2006-TR requires an attendance record in which each worker personally records clock-in and clock-out. The timesheet is filled in by the foreman. Peru's inspection regulation treats not having that record, or replacing the worker in it, as a very serious infraction. The site needs both, and they must match.
What columns should a construction timesheet have?
In the header: project, front, employer with tax ID, date and foreman. In each row: name, ID number, category, crew, cost item, regular hours, overtime hours and notes. At the bottom: total man-hours and man-hours per cost item, with the signatures of whoever filled it in and whoever reviewed it.
Is the timesheet daily or weekly?
It's filled in every day, at the front. The weekly sheet is the consolidation the administrator builds for payroll. If only the weekly one exists, hours get allocated from memory and cost per item stops being reliable.
How are man-hours per cost item calculated?
Add up the hours, regular and overtime, that every worker booked to that item over the period. Compared with the measured quantities in the daily report, they give the crew's real productivity, which is what gets checked against the budget.
Next step
If your site already has the format and what fails is consolidating it, reconciling it with attendance and seeing cost per item in time, that's what our Timesheet & Attendance accelerator solves, built on your project's operation in construction. Let's talk.
More from the field
SSOMA · 8 min read
Continuous IPERC: form, filling, examples, and when ATS applies
Continuous IPERC explained: what Annex 7 of DS 024-2016-EM requires, how to fill it out step by step, an example, and when an ATS applies instead.
SSOMA · 7 min read
Pre-use checklist for pickups and equipment: what the rules require
Pre-use checklist for pickups and heavy equipment on construction and mining sites: what to check, what DS 024-2016-EM requires, how to close faults.